|
|
 |
|
 |
| |
| |
|
| |
The Port Mann / Highway 1 Project - now well underway
- comprises of improvements and widening of Highway
1 from McGill Street in
Vancouver to 216th Street in Langley.
The project is of 37 kilometres in length, and comprises
of interchange construction to improve and replace many
of the interchanges which
were completed when the Port Mann / Cassiar Street section
of Highway 1 was opened in 1964.
Historical Background
- Port Mann Bridge opens on June 12,
1964.
|
|
1962
Chevron road map showing principal routes in the
Greater Vancouver area. Highway 99 from Ladner
to Vancouver is shown green as
it was a tolled route from its completion in 1959
to the removal of tolls on April 1st, 1964. The
new freeway from Abbotsford to Vancouver
was fully completed in 1964. Speed limit was 60
MPH (100 km/h) from Vancouver to the Port Mann
and 70 MPH (120 km/h) from Port Mann to the then
freeway's end in Bridal Falls east of Chillwack.
The Cassiar section was not completed until opening
in early 1991. |
|
|
The
Port Mann Bridge begins to span the Fraser River
in this view looking north east north to Port
Coquitlam. Mary Hill is in the distance,
the cut on the east side was a former large gravel
pit.
|
|
|
| The
Port Mann Bridge continues over the Fraser River
in this view west north west from Surrey to Coquitlam.
|
 |
| Click
on this sign to view news articles about the opening
of the new Port Mann Bridge in June, 1964 |
 |
|
 |
Completing
the Port Mann Bridge in 1964. This view is from
the Surrey side looking towards Coquitlam, |
|
Port
Mann Bridge after completion, at Surrey end. The
railings had a unique fixture, a continious florscent
lighting along the entire length of the bridge.
The lighting was replaced later with high mast
lights. |
The Greater Vancouver region at the time the Port Mann
Bridge and Highway 1 opened, had a population of approximately
750,000.
Historical Background
- HOV lane added in 1999.
The crossing did not receive any major upgrades until
November,1999 when a $60 million project to add a 5th
lane - an eastbound only
HOV lane - was begun. The project was completed in 2002.
The project comprised of placing the maintainance sidewalk
onto wingdecks,
removing the existing steel centre barrier, replacing
with a concrete safety barrier and widening the bridge
deck 1.5m on each side.
The project also included establishment of an on ramp
from the Lougheed Highway to westbound Highway 1 and
improvements to the Mary Hill bypass. At the time of
construction of the HOV lane, about 120,000 vehicles
a day were using the bridge.
The project was a continuation of an earlier completed
project to provide a westbound and eastbound HOV lane
from the Port Mann Bridge to
Grandview Highway in Burnaby/Vancouver.
|
This
equipment was used to move materials from one
side of the bridge to the other and to lift
materials from the surface during the
reconfiguration of the bridge. It resulted in
much less traffic disruption than using conventional
crane wheeled equipment. |
 |
|
 |
Original
configuration before widening. |
|
After
widening. The motorcyclist is using the
HOV lane. |
|
From Vancouver to Langley, Highway 1 is a heavily used
route for commercial vehicles and commuters and is well
beyond its original service capacity.
The Project
- Construction began on February 4, 2009.
The Port Mann Bridge, is being replaced with a new 10
lane structure that will also have features for cycling
across the Fraser River.
The new bridge is also designed to carry a future rapid
transit line. The new bridge was announced on February
4, 2009.
 |
|
 |
New
bridge design unveiled by Premier Campell
and
Minister of Transportation Kevin Falcon.
|
|
Dave
with project workers. Large pipes in the
background are
foundations for the piers. |
|
| |
|
The
new bridge from Surrey looking northeast. The
South Fraser Perimeter Road can be seen underneath.
|
|
Centre
section of the new bridge. Seperated lanes will
direct traffic to Coquitlam (westbound) and
Surrey (eastbound)
and provide express lanes for HOV and through
traffic. |
|
The
new bridge from Surrey looking northwest. |
| A
third of the way to completion. |
|
|
 |
|
 |
The
Premier along with Minister of Transportaton and
Infrastructure
Shirley Bond, MLAs Rich Coleman (Ft. Langley-Aldergrove),
Mary Polack (Langley) Harry Bloy (Burnaby-Lougheed)
Dave Hayer and Marc Dalton (Maple Ridge Mission)
note that as of July 22nd, 2010, the project is
one-third completed. |
|
The
east end of the new Port Mann Bridge takes shape.
The gantry
is a walking parallel beam structure that lifts
sections into place
where they are bonded with epoxy resin, sealed
and moves forward
to place more sections. The equipment is similar
to that used to
build the Millenium Line and above ground sections
of the Canada
Line. |
 |
|
 |
The
approach deck to the new bridge looking northeeast.
The piers
in the foreground have reached their design height
and will be ready
to be fitted with the top cap upon which the roadway
wlll rest. |
|
As
high as a 50 storey building, the east pier is
about 80% of the
way to being completed. The two tower piers will
be fitted with
encased cables to make up the cable stayed section
of the bridge |
More
pictures of the site and the 1/3 Completion Event
can be seen on Dave's
Photo Album page.
Go on a site visit to see the Surrey end of the
bridge project and the equipment used for placement
of the bridge
deck here!
View a You Tube video of the first sections of
Gantry Crane being moved and an interview with
Dave Hayer
Another site visit was completed in late April,
2011 visiting the Surrey and Coquitlam side. To
view pictures click
here! |
Another key feature of the project is the inclusion
of RapidBus servcie from Langley and Surrey to Lougheed
Maill to provide express service
to the Skytrain Line. With limited stops, a trip from
Langley to the Lougheed Skytrain station is expected
to take just 25 minutes. The new
RapidBus service will begin the day the new Port Mann
Bridge opens.
In Surrey Tynehead, there are many parts of the project.
Noise abatement barriers are an integral part of the
project, providing residential properties reduced sound
levels. Environmental protection
is also part of the project with earthworks and stream
enhancements.
Johnson Hill's earthworks will be widened to accomodate
the 10 lanes from the bridge and approaches to and from
156th Street. There will be minimal instrusion onto
private lands on either side. Much of the widening will
remove the existing cut slope to retaining walls.
|
The
slopes on either side of Johnson Hill will be
cut back to accomodate additional lanes. |
 |
|
 |
New
approach west of 156th Street, westbound. |
|
Approach
to the new bridge. |
156th Street's interchange is being reconfigured to
provide better direct access to the Port Mann Bridge
from Guildford. A key part of the
configuration is the building of westbound lanes dedicated
for traffic destined to the Tri-Cities (Coquitlam, Port
Coquitlam and Port Moody).
The earthworks at Johnson Hill will be widened out to
accomodate the 10 lane approach to the new Port Mann
Bridge.
A new 156th Street underpass opened in May 2009 provides
quick an easy access to the fast growing Fraser Heights
area. The underpass
will be expanded shortly to provide HOV access, and
a RapidBus stop. It is a key part of better access to
Fraser Heights
| |
 |
|
| |
156th
Street underpass looking north to Fraser Heights
and 104 Ave.
between the spans will be an intersection for
HOV access to Highway 1. |
|
160th Street's interchange is being realigned for ease
of traffic congestion and access to and from Highway
1 and improving acess to and from
Fraser Heights.
176th Street and Highway 1 interchange will be widened
and enhanced to provide improved access to Port Kells
and Pacific Highway, in addition to providing primary
access to the South Fraser Perimeter Road. The South
Fraser Perimeter Road - now starting construction -
will provide access
to the Fraser Surrey Docks, Delta's Tilbury Island industrial
area, and provide an excellent route for Coquitlam,
North Fraser and north Surrey
residents along with commerical traffic to Highway 99
and the Tsawwassen Ferry.
192nd Street interchange now completed provides access
to Surrey's Port Kells business and industrial area,
in addition to providing access to
the Golden Ears Bridge for efficient access to the growing
areas of Pitt Meadows and Maple Ridge.
|
| Construction
Progress |
 |
To
view construction progress on the project, move your
mouse over one of the highlighted locations.
There are 8 traffic camera (green squares) and four
construction camera pages (orange diamonds).
The maps can also be used to view current traffic conditiions.
Traffic cameras refresh about once every two minutes,
construction cameras
refresh each hour and have both east and west views
from the camera location. |
| Construction
Schedule |
 |
| This
sheet provides a construction schedule for the project
and the many elements that are a part of it. Click to
view. |
| Project
Information |
This
collection of documents will provide information
about the project. Construction updates are provided
when available.
Construction updates and bulletins are for sections
of the project between the Port Mann Bridge and
192nd Street in Surrey.
To view updates for the entire project plus bulletins
presented in 2009, click [ here
] |
 |
|
 |
|
 |
|
Project
Fact Sheet
|
|
Community
Update
|
|
Environmental
Update
|
 |
|
 |
|
 |
|
Project
Update
|
|
Fraser
Heights Discussion Guide
(outlines 152nd Street features)
|
|
Community
Update July 2010
|
| Highway
1 - Port Mann Bridge |
 |
|
 |
|
 |
|
Bridge
Construction begins
|
|
In-River
Construction
|
|
Construction
Update (August 2009)
|
 |
|
 |
|
 |
|
Construction
Update
(December 2009)
|
|
Oversize
Loads Crossing
(May 2010)
|
|
80
km/h Speed Limit
( July 2010 )
|
| Highway
1 - Johnson Hill to 160th Street |
 |
|
 |
|
 |
|
Johnson
Hill Activity
|
|
152nd
Street Interchange
|
|
160th Street Interchange
|
 |
|
 |
|
 |
|
152nd
Street Interchange
(July 2010)
|
|
152nd
Street Interchange
Update - Summer 2010
|
|
152nd
Street Interchange
|
 |
|
 |
|
 |
|
Hwy
1 Eastbound at 152
|
|
Hwy
1 Eastbound at 152
(Left Lane Exit Change )
|
|
156th
Overpass Construction
|
 |
|
|
|
|
|
156th
Street Interchange
Update - December 2010
|
|
|
|
176th
Street
Update - Spring 2011
|
| Highway
1 - 160th Street to 192nd Street |
 |
|
 |
|
 |
|
160th
Street Interchange
Night Detour
|
|
160th
Street Interchange
Detour
|
|
160th
Street Interchange
Detour
|
 |
|
 |
|
 |
|
Traffic
Pattern Change
160h Street
|
|
Traffic
Pattern Change
160h Street (June 2011-2012)
|
|
160th
Street
Update - Summer 2011
|
 |
|
 |
|
 |
|
Eastbound
Weigh Scale
Lane Shift
|
|
Construction
ramps at
176th Street
|
|
176th
and Barnston Drive
|
 |
|
 |
|
 |
|
176th
Interchange
|
|
176th
Pattern Change
|
|
Traffic
Pattern Change
176th Street
|
 |
|
 |
|
 |
|
Traffic
Pattern Change
Abby Drive / 100 Ave 176th Street
|
|
176th
Street
Update - Spring 2011
|
|
176th
Street
Update - Summer 2011
|
|
|
For
additional information or questions about the Port
Mann Bridge / Highway 1 proejct, please contact my
office.
My friendly and knowledgeable staff will be most happy
to assist and receive your inquiries.
|
|
|
 |
 |
 |
This
site is provided as a public service at the request of the Member
of the Legislative Assembly and is external to the B.C. Govenrment
Legislative Assembly web site.
The Legislative Assembly Office does not control, monitor or guarantee
the information contained in this site and does not endorse any
views expressed therein.
|
|